Decree No. 51 / 2006 Coll.
Order on the conditions of connection to the electrical system
Valid
Effective from 01.03.2006
Zobrazeno prvních 200 z celkem 341 ustanovení tohoto předpisu.
Zobrazit celý předpis →
Pro stažení celého znění použijte tlačítko Stáhnout výše.
51
DECLARATION
of 17 February 2006
on the conditions for connection to the electricity system
Pursuant to § 98 (7) of Act No. 458 / 2000 Coll., on the Terms and Conditions of Business and on the Enforcement of State Administration in the Energy Sector and on the Amendment of Certain Laws (Energy Act), as amended by Act No. 670 / 2004 Coll., for the implementation of § 17 (7) (d) and (h) of the Energy Act:
Subject matter
This decree sets out the conditions for the connection of electricity generation, distribution systems and customer demand points to the electricity system and the way in which the cost ratio associated with the connection and the provision of the required power input is determined.
Basic provisions
For the purposes of this decree:
(a) reserved power
1. the value of the power input at the transmission point in MW in basic connection agreed with the transmission system operator on the basis of the required power input and the technical parameters of the transmission system equipment at the transmission point; or
2. the value of the electrical input agreed with the distribution system operator on the basis of the required power input for the sampling point or transmission point in kW at a very high or high voltage level or at the nominal value of the main circuit breaker before the electric meter in A at a low voltage level;
(b) reserved performance
1. the value of the connected power of the power plant at the transmission point of the transmission system in MW in basic connection, minus the value of the electricity consumption for electricity or electricity and heat generation;
2. the value of the connected power of the power plant at the transmission point of the distribution system in kW, reduced by the value of the electricity consumption for electricity generation; or
3. the value of power in MW agreed with the TSO for the distribution system transfer point or agreed with the distribution system operator for the transfer point of another distribution system;
(c) the connection point - the point in the transmission or distribution system in which the installation is connected, directly, through the home installation or through the connection and home installation,
(d) equipment - electricity generation, distribution system or demand facility;
(e) the applicant - a natural or legal person who requests the connection of a transmission or distribution system installation or an increase in the reserved power or power of an existing installation and who is entitled to use the installation on the basis of a right of ownership or otherwise; a natural or legal person intending to build an installation in the territory concerned shall also be considered as an applicant.
Conditions for connection of the applicant to the transmission system or distribution system
(1) The conditions for connection of the applicant's equipment to the transmission or distribution system shall be:
(a) the submission of an application for connection;
(b) the submission of a study of accessibility under the conditions laid down in § 4a;
(c) the conclusion of a connection agreement between the applicant and the transmission system operator or distribution system operator or the modification of the existing connection contract (1).
(2) The applicant shall only submit an application for the conclusion of a connection contract or an amendment to an existing connection contract where there is no change in the technical terms of the connection
(a) a change of the licence holder operating the installation without interruption of the connection of the electricity plant to the transmission or distribution system; or
(b) the replacement or modification of a power plant where the existing contracted amount of the reserved power is not exceeded while maintaining the standard conditions for transmission or distribution of electricity.
(3) The first change in the electricity supplier shall be carried out in accordance with the Electricity Market Regulation (2) setting out the dates and procedure for changing the electricity supplier.
(4) The reimbursement of the share of the costs associated with the connection and the provision of the required input or output (hereinafter referred to as the "proportion of eligible costs") shall not apply in the cases referred to in paragraph 2 or 3 or where the share of eligible costs has already been paid by another natural or legal person. This is not the case if the period of reservation of the power according to § 7 (7) to (9) has expired.
(5) Where an applicant who is the parallel holder of electricity distribution and electricity production licences is requested to be connected, it shall be deemed to request the connection of the distribution system, unless the technical documentation shows that the connected installation is a power plant. Where the installation of an electricity market participant which is the parallel holder of the electricity distribution and production licences already connected to the transmission system or distribution system is considered to be connected, the distribution system shall be deemed to be connected unless the technical documentation shows that the connected installation is of the nature of the electricity generation plant.
(6) Electricity production can also be connected at the sampling point. The customer requests the connection of the electricity plant at the sampling point. The connection of the power plant to the transfer point of another power plant shall be as if the connection of the power plant at the sampling point is carried out.
(7) Where an applicant holding a power distribution licence or a power production licence requests a connection to a transmission system or distribution system, both the reserved power and the reserved power shall be reserved for the transfer point.
Application for connection of a transmission or distribution system
(1) The application shall be submitted for each sampling or transfer point separately. A request for the connection of the applicant to the transmission system or distribution system shall be submitted:
(a) prior to the construction or connection of a new installation;
(b) before increasing the reserved power or power of the existing connected equipment;
(c) prior to the change in the nature of the sampling provided for in Annex 7 to this Decree;
(d) in the event of a change in the type of electricity generation plant;
(e) in the event of a change in the connection point of the electricity plant to the transmission system or distribution system.
(2) The elements of the request for the connection of a power plant or part of it to a transmission or distribution system are set out in Annex 1 to this Decree.
(3) The application for connection of a power plant shall include the consent of the owner of the property to the location of the power plant on its real estate and, in the case of the power plant, the installed power
(a) between 30 kW and 5 MW, including zoning information on the conditions under which the zoning decision is made, showing that the construction of the electricity plant is in line with the zoning documentation;
(b) above 5 MW connected to the distribution system and the electricity generation plant connected to the transmission system by zoning information on the conditions of the territorial decision;
(c) above 0,5 MW the timetable for preparing the construction of the electricity plant.
(4) The schedule for the preparation of the construction of the electricity production plant contains a list of decisions, opinions and comments by public authorities and the envisaged dates for their publication, in particular as regards the conclusions of the environmental assessment procedure, the location of the construction site, the integrated permit, the permit of the construction and the approval of the building and the approval of the building of the power plant.
(5) The details of the request for connection to the transmission system or distribution system are set out in Annex 2 to this Regulation.
(6) The requirements of the request to connect a demand facility to the transmission system or distribution system from a voltage level of particularly high voltage, very high voltage and high voltage are set out in Annex 3 to this Decree.
(7) The elements of the request for the connection of a demand facility to the distribution system from the low voltage voltage voltage voltage level are set out in Annex 4 to this Decree.
Addendum studies
(1) The transmission system operator or distribution system operator may require the applicant to process a study of the connectivity,
(a) if, taking into account all circumstances, it is clear that the installation for which the applicant requests connection will affect the reliability of the operation of the transmission system or distribution system; or
(b) when the device is requested to be connected to a voltage level of high voltage and higher.
(2) Where an applicant requests a transmission system connection or an increase in the reserved power or power at the transmission point between the distribution and transmission system, the transmission system operator and the distribution system operator shall jointly ensure the processing of the appendability study.
(3) The study of the connectivity of a power plant or demand facility shall assess the expected effects of the connection of an installation on the reliability of the operation of the transmission system or distribution system. In addition, an assessment of possible variants of the required connection in terms of cost is the subject of a study of the connection of the transmission system or distribution system to another distribution system.
(4) The transmission system operator or distribution system operator may request the processing of a study of the connectivity within 30 days of the request for connection. At the same time, it must define the required extent of the study of connectivity.
(5) If the applicant requests the TSO or the distribution system operator to provide documentation for the processing of the addendum study no later than 30 days after receipt of the request for processing, the TSO or the distribution system operator shall provide the applicant with the necessary documentation for the processing of the attachment study within 15 days of their request. If the applicant does not request the transmission system operator or distribution system operator to provide documentation for the processing of the addendum study within 30 days of receipt of the request for processing, the transmission system operator or distribution system operator shall not consider the connection request.
(6) Where the transmission system operator or distribution system operator does not request the processing of the appendability study within the time limit referred to in paragraph 4, or does not provide the applicant with the necessary documentation for the processing of the appendability study, it shall be deemed not to require the processing of the appendability study.
(7) The applicant for connection to the distribution system shall submit to the distribution system operator a study of the connectivity within 90 days of the date on which the distribution system operator transmitted to the applicant the documentation necessary for the processing of the study. Where an applicant requests a connection to a transmission system, the applicant shall transmit to the transmission system operator a study of the connectivity within 180 days of the date on which the transmission system operator transmitted to the applicant the documentation necessary for the processing of the study, unless otherwise agreed between the applicant and the transmission system operator.
(8) In the absence of an attachment study to the extent defined by the transmission system operator or distribution system operator, the transmission system operator or distribution system operator may request its completion or extension. The transmission system operator or distribution system operator may request the addition or extension of the appendability study no later than 30 days after the transmission of the appendability study.
(9) If the TSO requests the addition or extension of the appendicibility study, the applicant shall transmit the additional or extended appendicibility study within 90 days of receipt of the request by the TSO, unless otherwise assessed. Paragraph 7 shall apply mutatis mutandis for the processing and transmission of a new study of the connectivity.
(10) If the distribution system operator requests the addition or extension of the appendicibility study, the applicant shall transmit the additional or extended appendicibility study within 30 days of receipt of the request by the distribution system operator. Paragraph 7 shall apply mutatis mutandis for the processing and transmission of a new study of the connectivity.
Assessment of the request for connection of a transmission or distribution system
(1) The transmission system operator or distribution system operator shall assess the application for the connection of the installation with regard to:
(a) the location and manner of the required connection;
(b) the size of the required reserved power or power and the time course of load;
(c) reliability of electricity supply;
(d) the nature of the reactivity of the applicant's equipment on the transmission or distribution system;
(e) planned development of the system;
(f) the sequence of applications submitted; and
(g) the associated power limits to the electricity system established by the TSO.
(2) Where necessary for an appropriate assessment of the connection request, the TSO or the distribution system operator shall invite the applicant no later than 15 days from the date of receipt of the request to supplement the data provided to the extent necessary and shall set a reasonable deadline. At the same time, the applicant shall indicate that the application will not be considered if the data to the extent requested are not completed.
(3) Where the applicant has been requested to supplement the data provided pursuant to paragraph 2 and the applicant has not done so, the TSO or distribution system operator shall not assess the request. It shall communicate this to the applicant without undue delay.
(4) If the reasons set out in the Energy Act for which the transmission system or distribution system operator cannot be connected (3) are not provided, the distribution system operator shall submit to the applicant within 30 days or, in the case of an installation connected to a voltage level of high or very high voltage within 60 days of the submission of a complete request for connection or from the date of transmission of the study of the appendability, a draft connection contract or a draft future connection contract. In the case of an installation connected to a transmission system, the time limit for the submission of a draft connection agreement or contract shall be 90 days from the date of submission of the complete request for connection or the date of transmission of the study to the connection if the study was requested to be processed. The transmission system operator or distribution system operator shall determine in the draft contract future connection or connection contract a time limit for the acceptance of the draft contract of 30 days when the connection of the device to the low voltage voltage voltage voltage level or 60 days when the connection to the high voltage voltage level is concerned.
(5) If the installation of the applicant cannot be connected for reasons specified by the Energy Act (3), the transmission system operator or distribution system operator shall inform the applicant in writing within 30 days of the submission of the complete application for connection or from the date of transmission of the appendability study if the processing of the appendability study has been requested. At the same time, the transmission system operator or distribution system operator shall state the specific reasons for which the applicant's installation cannot be connected. However, if the installation of the applicant can be connected under other conditions and from the content of the application or from the circumstances in which the application was made, it may be assumed that the applicant will be interested in such connection, the TSO or the distribution system operator shall communicate in writing to the applicant such fact, including the reasons for which the installation cannot be connected under the required conditions, and submit to the applicant a draft contract pursuant to paragraph 4.
(6) The future connection contract is concluded as a general rule if the connection of the applicant's equipment requires construction technical measures in the transmission system or distribution system, the implementation of which requires a decision on the location of the construction or territorial consent under the construction law.
(7) Where measurements are necessary for the assessment of the request for connection or for a 110 kV network, the time period referred to in paragraph 4 or 5 shall be extended by a maximum of 30 days. The transmission system operator or distribution system operator shall inform the applicant of the necessity of measuring or verifying the operation of the network and of the extension of the deadline within 15 days of the date of receipt of the connection request at the latest.
(8) The transmission system operator or distribution system operator shall propose the connection of the installation in such a way that the technical execution of the connection of the installation is based on the planned development of the system, taking into account the applicant's interest in minimising the costs of connecting the transmission or distribution system.
(9) The transmission system operator or distribution system operator shall reserve the requested power or power from the time the draft contract is submitted in accordance with paragraph 4.
(10) If the applicant does not accept a draft contract within 30 days for connection to a low voltage voltage voltage voltage level or within 60 days for connection to a high voltage voltage voltage level and higher, the power reservation or power reservation shall cease.
Short term connection to the distribution system
(1) Short term connection means the connection of a provisional installation according to the Czech technical standard (4) to a fixed-term distribution system.
(2) In the case of short-term connection, the applicant shall submit a request for short-term connection to the distribution system separately for each sampling or transfer point. The details of the applicant's application for short-term connection are set out in Annex 5 to this Decree.
(3) Paragraphs 4 to 5 and 7 shall apply mutatis mutandis to short-term connections. The location of the connection shall preferably be determined in such a way as to avoid the need for the costs of the connected distribution system operator.
(4) Where the distribution system operator incurs costs related to ensuring the short-term connection of the applicant's equipment, the applicant for short-term connection to the distribution system shall pay the costs associated with the connection, including the cost of putting the connection point at the end of the withdrawal in full. The share of the eligible costs under Paragraph 10a shall not be reimbursed.
(5) On termination of the connection contract, the reservation of the power will cease; Paragraph 7 (7) to (9) shall not apply.
(6) If, due to the implementation of short-term connection to the distribution system, there is a need for an increase in the reserved power at the transfer points between the distribution system at which the short-term connection took place and another distribution system, the procedure shall be followed in accordance with paragraph 4.
Connection of the applicant's equipment to the transmission or distribution system
(1) The connection of the applicant's equipment to the transmission or distribution system shall take place under the connection contract.
(2) A contract to connect one applicant may include several sampling or transfer points, provided that each of them is separately stated in the contract.
(3) The applicant will pay an advance on the share of the eligible costs referred to in Annex 6 to this Order, amounting to 50% of the value of the share of the eligible costs, but not more than CZK 50 000 000. The applicant shall pay an advance on the share of the eligible costs within 15 days of the date of conclusion of the connection contract or future connection contract.
(4) If the applicant fails to pay an advance on the share of the eligible costs referred to in paragraph 3 or within an additional reasonable period provided by the transmission system operator or distribution system operator and the transmission system operator or distribution system operator or distribution system operator for this reason, the connection contract or future contract for connection, reservation of performance or reservation of power by the termination of the contractual relationship shall be terminated.
(5) If the connection of the applicant's equipment does not require the implementation of construction technical measures in the transmission system or distribution system, the transmission system operator or distribution system operator and the applicant shall agree the date of connection of the solar power plant in such a way that the power plant is connected no later than 180 days after the date of conclusion of the connection contract, in the case of a solar power plant with an installed power output exceeding 30 kW within 1 year of the date of conclusion of the connection contract.
(6) Where the applicant demonstrates, within the time limits referred to in paragraph 5, that, despite all the efforts made, no extension of the connection time has taken place within the agreed time-limit for reasons which arise or exist independently of his will, the TSO or the distribution system operator shall agree with the applicant an extension of the connection time of the necessary time.
(7) If a reduction in the value of the main circuit breaker is agreed before the measuring device to a value lower than that of the reserved power input of the client's device for more than 24 months, the value of the reserved power input shall be reduced to that value.
(8) If, for 60 months from the date of the last change to the reserved power, no booked capacity of at least 90% of the reserved power has been negotiated, the value of the reserved power shall be reduced to the value given by the highest agreed size of the reserved capacity within 60 months of the last change to the reserved power.
(9) In the event of the termination of the electricity transfer or distribution contract, the reserve of power for the existing connection point shall last for 60 months from the date of termination of the contract. If the electricity transfer or distribution contract has not been concluded within 60 months of the date of the connection agreed in the connection contract, the reserve of the power for the sampling point or the connection point shall cease.
Costs associated with the connection of the transmission or distribution system and the provision of the required power or power
(1) Where, under this Order, the applicant pays the costs associated with the connection and the provision of the required power or power in full, only the costs referred to in paragraphs 2 to 4 may be included in the costs borne by the applicant.
(2) The costs associated with the connection and the provision of the required power or power shall include the necessarily necessary legitimate costs incurred in connection with the acquisition, construction or modification of the transmission system or distribution system, which have been triggered by the applicant's request in relation to the location and the way in which its equipment is connected. The acquisition, construction or modification of a transmission system or distribution system shall be provided to the extent necessary, appropriate to the value of power input or power required by the applicant, and to the location and connection of its equipment.
(3) The cost of acquiring project documentation, geodetic orientation, material burdens and other direct related investment costs and charges for the construction, modification or acquisition of a transmission system or distribution system shall be included in the costs associated with the connection and the provision of the required input or power.
(4) The costs associated with the connection and the provision of the requested power input or power shall not include costs related to the acquisition, construction or modification of the transmission system or distribution system, which, in their scope, exceed the necessary level of power input or power required by the applicant and the location and connection of its equipment.
(5) The construction and modification of the transmission system is defined from the point of connection of the applicant's installation to the nearest point in the transmission system where the required reserved power or power is or would be available after making the necessary adjustments in the system.
(6) The construction and modification of the distribution system is defined from the point of connection of the applicant's equipment to the nearest point in the distribution system at the same voltage level where the required reserved power or power is or would be available after making the necessary adjustments in the system.
Share of eligible costs by the applicant for connection to the transmission system or distribution system
(1) The applicant's share of the eligible costs shall be calculated as the product of the specific proportion referred to in Annex 6 to this Order and the applicant of the requested reserved power or power.
(2) In the case of connection of a power-generating facility to a transmission or distribution system, the supply line shall be fully reimbursed by the applicant to the connection point.
(3) Where the power and power of one applicant are simultaneously reserved at one point of connection, the share of the eligible costs shall be determined separately for the reserve power and for the reserve power. The applicant shall pay a higher of the two agreed share of the eligible costs.
Re-connection of transmission or distribution systems
Where the transmission system operator or distribution system operator attaches a customer's demand facility to which the supply of electricity has been restricted or interrupted due to the unauthorised collection, transmission or distribution of electricity, the customer shall pay a share of the eligible costs of:
a) CZK 1,500 when connected to low voltage voltage voltage,
b) CZK 3,500 when connected to high voltage voltage voltage or higher.
Specific requirements of the applicant for connection to the transmission or distribution system
(1) If the applicant requests connection beyond the standard connection of the installation or requests a specific way of building or technical connection of the transmission system or distribution system, the applicant shall bear the eligible costs associated with the implementation of the superstandard connection or the specific construction or technical design of the connection in full.
(2) Low voltage reserve power may be transferred within one or more adjacent real estate only if technically possible and the execution of the reserved power transfer does not entail additional costs related to the acquisition, construction or modification of the distribution system. Similarly, transfer of the reserved power at high or very high voltage levels within a single node area of the relevant voltage level shall be carried out.
(3) Where an applicant requests the installation to be connected at a voltage level other than that to which the installation is connected and the requested change of connection is not required by a change in the technical conditions of connection, the applicant shall bear the costs of the eligible costs associated with the change in full. In such a case, a share of the eligible costs under Section 10 shall not be reimbursed up to the amount of the original reserved power or power. Paragraph 7 (7) to (9) shall not apply.
Electrical connection for electricity supply
(1) The length of the electrical connection is the length of the shortest construction and technically feasible route of the connection projected into the ground plan between the point of departure from the distribution system and the main house fuse or main home cable box.
(2) A vertical part of the electrical connection shall not be counted.
(3) In order to assess whether an electrical connection is in or outside the built-up territory under the Building Act (5), the location of the connected real estate is crucial.
Conditions for the supply of electricity in the event of a failure on the sampling and measuring equipment and in case of refusal of access to the measuring equipment
(2) If, due to a failure in the demand facility or a failure caused by the final customer on the measuring device, the transmission or distribution system operator restores the transmission or distribution system on the basis of a notification by the final customer of the removal or distribution of electricity on the demand facility within a time limit specified by the specific legislation7). The costs of restoring the transmission or distribution of electricity shall be borne by the final customer.
Transitional provisions
Where the applicant requests, on the basis of an opinion of the transmission or distribution system operator issued in accordance with existing law, a connection agreement, the transmission or distribution system operator shall, prior to the conclusion of the connection contract, re-evaluate the opinion issued within 30 days of the date of receipt of the request so that it complies with this decree. In determining the amount of the applicant's share of the costs associated with the connection and the provision of the required power or power shall be treated according to the legislation more favourable to the applicant. The transmission or distribution system operator shall submit a draft connection agreement to the applicant at the same time as the opinion reviewed. The original period of validity of the opinion under existing legislation shall be extended by the period during which the opinion was re-evaluated in accordance with the previous sentence.
Repeal
The following shall be deleted:
1. Decree No. 297 / 2001 Coll., laying down the conditions of connection and supply of electricity to protected customers.
2. Decree No. 18 / 2002 Coll., on the conditions of connection and transport of electricity in the electricity system.
3. Decree No. 300 / 2003 Coll., amending Decree No. 18 / 2002 Coll., on the conditions for connection and transport of electricity in the electricity system.
Efficacy
This Decree shall take effect on 1 March 2006.
Chairman:
Ing. Fiøt v. r.
Příloha č. 1
Annex No 1 to Decree No 51 / 2006 Coll.
OBLIGATIONS OF THE REQUEST FOR THE ACCESS OF THE ELECTRICITY PRODUCTION TO THE TRANSPORT SYSTEM OR DISTRIBUTION SYSTEM
1. Business company (completed by the applicant - entrepreneur registered in the Commercial Register).
2. Data on registration in the Commercial Register (completed by the applicant - entrepreneur registered in the Commercial Register).
3. Name or surname (completed by the applicant not registered in the Commercial Register).
4. Date of birth (completed by the applicant - natural person).
5. Location broken down: State, county, municipality with postal code, street and descriptive number, or registration number (completed by the applicant - legal person).
Place of business broken down: State, county, municipality with postal code, street and descriptive number, or registration number (completed by the applicant - natural person undertaking).
6. Name and surname of the person who is the statutory authority or of all persons who are members of the statutory authority (completed by the applicant - legal person).
7. Address of the place of stay broken down: State, Region, Municipality with postal code, street and descriptive number, or registration number (completed by the applicant - natural person not engaged).
8. Connection - phone, email.
9. Address for delivery.
10. Information about the data box if it has been set up.
11. Identification number, if assigned.
12. Tax identification number if assigned.
1. The location of the electricity plant - region, municipality, cadastral territory, partition numbers of the land on which the electricity plant is situated, descriptive number and, where applicable, registration number.
2. Type of electricity plant.
3. The character of electricity production.
4. Required date of connection.
5. Basic data on electricity generation:
5.1. Involvement of the power plant into the transmission system or distribution system (voltage level, estimated location of connection, single-pole scheme, territorial variants of individual connections),
5.2. Description of the power plant [total installed power of the power plant, available power of the power plant, power of individual blocks, electrical diagram of blocks, type of block (coal, gas, water, other), type of source (peak, base), produced energy per year, rated power factor, estimated block reliability],
5.3. description of block transformer (type, installed power, rated voltage, short voltage, winding connection, conversion, range of turns, short loss and empty loss, short-circuit resistance, etc.),
5.4. a description of the generator (type, installed output both apparent and active, rated voltage, connection, type of driver, switch, dynamic constants such as replacement reactances, time constants, inertia constants),
5.5. a description of the actual consumption (total installed power input, rated voltage, power factor, current).
6. Required reliability of performance.
The applicant declares and confirms with its signature the accuracy and veracity of all the above data.
Příloha č. 2
Annex No 2 to Decree No 51 / 2006 Coll.
OBLIGATIONS OF THE APPLICATION FOR ACCESS OF THE DISTRIBUTION SYSTEM EQUIPMENT TO THE TRANSFER SYSTEM OR DISTRIBUTION SYSTEM
1. Business company (completed by the applicant - entrepreneur registered in the Commercial Register).
2. Data on registration in the Commercial Register (completed by the applicant - entrepreneur registered in the Commercial Register).
3. Name or surname (completed by the applicant not registered in the Commercial Register).
4. Location broken down: State, county, municipality with postal code, street and descriptive number, or registration number (completed by the applicant - legal person).
Place of business broken down: State, county, municipality with postal code, street and descriptive number, or registration number (completed by the applicant - natural person undertaking).
5. Name and surname of the person who is the statutory authority or of all persons who are members of the statutory authority (completed by the applicant - legal person).
6. Connection - telephone, email.
7. Address for delivery.
8. Information about the data box if it has been set up.
Sign in for notes, favorites and notifications
Regulation Information
| Citation | Decree No. 51 / 2006 Coll., on the Conditions of Connection to the Electricity System |
|---|---|
| Regulation Type | - |
| Author | - |
| Collection | Code of Laws |
| Date of Promulgation | 28.02.2006 |
|---|---|
| Effective from | 01.03.2006 |
| Effective until | - |
| Status | Valid |
The regulation text is for informational purposes only.
Comments 0