Decree of the Ministry of Industry and Trade No. 34 / 1999 Coll.
Decree of the Ministry of Industry and Trade amending Decree of the Ministry of Industry and Trade No. 95 / 1998 Coll., laying down the dispatching order of the electricity system of the Czech Republic
Valid
Order
Effective from 23.02.1999
Text versions:
23.02.1999
34
DECLARATION
Ministry of Industry and Trade
of 5 February 1999
amending Decree of the Ministry of Industry and Trade No. 95 / 1998 Coll., establishing the Dispatching Order of the Electrical System of the Czech Republic
The Ministry of Industry and Trade provides pursuant to Articles 13 (7) and 45 (6) of Act No 222 / 1994 Coll., on the Terms and Conditions of Business and on the Performance of State Administration in the Energy Sector and on State Energy Inspection, as amended by Act No 83 / 1998 Coll.:
Decree No. 95 / 1998 Coll., establishing the dispatching order of the electricity system of the Czech Republic, is amended as follows:
1. In Section 1, paragraph 7 is added:
"(7) Dispatcher's instructions include:
(a) the Directive of the Central Electricity Dispatch of the Czech Republic ("Central Dispatch"),
(b) the operational instructions of the dispatches referred to in Section 2 as well as their instructions in the operational management of the operation of the electricity system pursuant to Section 7. ';
2. in Article 2 (1) (a):
"(a) by a central dispatcher,"
3. in Article 2 (1) (b), the words "dispatching holder of the power distribution authorisation - ČEZ, a. s., hereinafter referred to as" dispatching ČEZ "shall be replaced by" dispatching system. "
4. In Article 2 (3), the words "and the control of the frequency of the electricity system 'shall be inserted after the word" system'.
5. in Article 2 (3) (a) and (b), the words "CEEZ dispatcher" shall be replaced by the words "Transmission dispatcher."
6. In Paragraph 6 (2), "ČEZ dispatching unit 'is replaced by" Transmission system dispatching unit';
7. In Article 6 (4), the words "ČEZ dispatcher 'are replaced by the words" transmission dispatcher'.
8. In Article 6 (5), the words "ČEZ dispatcher 'are replaced by the words" transmission dispatcher'.
9. In Article 6, the following paragraph 6 is added:
"(6) The procedure for processing the annual preparation of the operation of the electricity system is set out in Annex 1."
10. in Article 7 (1) (b), a comma is added after the word "load" and the words "between parallel production facilities" are replaced by the words "method of allocating resources."
11. in Article 7 (3) (a), the words "CEEZ dispatcher" are replaced by the words "transmission dispatcher."
12. in Article 7 (3) (b), the words "CEEZ dispatcher" are replaced by the words "transmission dispatcher."
13. In Paragraph 7, the following paragraph 5 is inserted after paragraph 4:
"(5) The method of allocation of resources is set out in Annex 2."
14. In Paragraph 7, paragraph 5 is renumbered paragraph 6 and the heading "1 'is replaced by" 3'.
15. In Paragraph 7, paragraph 6 is renumbered paragraph 7 and "2 'is replaced by" 4'.
16. Annex 1 shall read as follows:
"Annex No 1 to Decree No 95 / 1998 Coll.
Procedure for processing the annual preparation of the operation of the electricity system
1. Content of the annual preparation of the operation of the electricity system
The annual preparation of operations shall include in particular:
1.1 the expected amount of load after months including its structure;
1.2 type load diagrams of the electricity system for working days and working and rest days for each month and diagrams of expected critical conditions (e.g. maximum, minimum load of the year),
1.3 the balance of electrical performance, including international cooperation after weeks,
1.4 the balance of electricity after months, broken down into resources and consumption, including international cooperation, with respect for the principles of uniform management of the electricity system and the efficient use of resources with a power output above 50 MW;
1.5 calculation of the reliable operation of the electricity system,
1.6 draft measures to ensure the reliable functioning of the electricity system;
1.7 the basic scheme for the involvement of transmission and distribution systems (in relation to the transmission system), the maintenance and shut-down plan for transmission and distribution system (in relation to the transmission system) and the putting in service of new equipment or the decommissioning (if applicable) of equipment,
1.8 control of selected modes in terms of network operation, check of static and dynamic stability, calculation of short-circuit ratios for a given year, capacity of transmission system transformation to distribution systems, and compensation for voltage and reactive power management;
1.9 the amount and composition of the electrical performance needed to ensure the reliability of the operation of the electricity system and the international interconnection and their comparison with the annual balance results;
1.10 results of the final discussion of the annual preparation of the operation of the electricity system.
2. Processing of the annual preparation of the operation of the electricity system
2.1 Transmission of documentation for the processing of annual preparation of operations, namely:
2.1.1 expected load type diagrams for working and rest days and off days for each month,
2.1.2 specified outputs from the annual balance and data resulting from existing and / or planned contractual relations needed to establish the balance of electricity and electricity; the supporting documents are in particular:
2.1.2.1 the electricity balance in the structure of the electricity purchase plan from producers (over 10 MW, namely, up to 10 MW including sum), imports of electricity from abroad, supply of electricity (broken down collectively for very high and high voltage consumption and further low voltage consumption), exports to abroad, other and own consumption and network losses,
2.1.2.2 a breakdown of the ready-to-use performance of the blocks (above 10 MW by name, up to 10 MW including sum), the indication of the regulatory capabilities of the blocks, the breakdown of tests and measurements and technical limitations on operation,
2.1.2.3 information on changes in performance in nodal areas against the fact of last year above 10 MW; the technical feasibility of the existing contractual relations of the relevant distribution facility users is already verified in these documents,
2.1.3 a plan for the maintenance and restoration of distribution installations and the putting into service or decommissioning of new installations;
2.1.4 short-term contributions from the authorisation holder's network to the transmission system distribution,
2.2 identification of possible situations where the conditions for the reliability of the operation of the electricity system and international interconnection are not met,
2.3 use of knowledge from the evaluation of the annual operations preparation of previous years;
2.4 proposing measures to eliminate situations where the conditions for the reliability of the operation of the electricity system and international interconnection are not met, namely:
2.4.1 changes in the dates of planned outages of energy production facilities,
2.4.2 changes in the installation mode;
2.4.3 changes in planned contractual supplies,
2.4.4 additional imports or exports of electricity,
2.4.5 changes to the switching off plan;
2.5 joint meetings shall take place with the participation of the authorised representatives of the bodies concerned, the central dispatcher and the Ministry of Industry and Trade in cases where no agreement is reached between the authorisation holders on the proposed measures under point 2.4,
2.6 a comparison of the annual balance and the draft annual preparation of operations, in particular concerning supply requirements and the level and composition of electrical performance to ensure the reliability of the operation of the electricity system and the international interconnection,
2.7 sending the draft annual preparation of the operation of the electricity system to the central dispatcher and its members;
2.8 final discussion of this proposal by the central dispatcher and acquisition of the minutes,
2.9 issue of the document "Annual preparation of operations for the year....."
3. Evaluation of the annual preparation of the operation of the electricity system shall be carried out by 31 May of the following year. ';
17. Annex 2 shall read as follows:
"Annex No 2 to Decree No 95 / 1998 Coll.
Resource allocation method
1. Resource management means:
1.1 release from service and re-entry into service;
1.2. Distribution of load between parallel operating sources.
2. The distribution of resources shall be carried out at the appropriate dispatch of the authorisation holder to the distribution for resources under its control.
3. The allocation of resources shall be carried out in such a way that, while ensuring the reliability of the operation of the electricity system, electricity is supplied at the lowest cost.
4. In cases of large-scale failures in the electricity system and in the prevention and management of emergency situations, the priority criterion for allocating resources is to restore reliable electricity supply in the electricity system.
5. Sources whose performance or part thereof is directly applied to the daily load diagram are:
5.1. Heat and electricity combined sources,
5.2. Resources used for electricity generation by renewable and secondary energy sources,
5.3. Resources for which electricity generation is intended for own use,
5.4 hydropower plants whose electricity generation is linked to hydrological conditions and to compliance with hydraulic connections,
5.5. Resources whose operation is determined on the basis of local conditions of the electricity system,
5.6. Sources whose ranking is triggered by the operating conditions of the electricity system, in particular by carrying out measurements and tests on equipment;
5.7. The resources for which this method of deployment results from contracts concluded between authorisation holders.
6. The allocation of resources shall be based on maintenance plans and timetables for nuclear fuel exchanges.
7. Other sources with a unit power greater than 50 MW shall be deployed in accordance with point 3 of this Annex. ';
18. Annexes 1 and 2 shall be renumbered Annexes 3 and 4.
This decree shall take effect on the day of its publication.
Minister:
Doc.
Sign in for notes, favorites and notifications
Regulation Information
| Citation | Decree of the Ministry of Industry and Trade No. 34 / 1999 Coll., amending Decree of the Ministry of Industry and Trade No. 95 / 1998 Coll., establishing the dispatching order of the electricity system of the Czech Republic |
|---|---|
| Regulation Type | Order |
| Author | - |
| Collection | Code of Laws |
| Date of Promulgation | 23.02.1999 |
|---|---|
| Effective from | 23.02.1999 |
| Effective until | - |
| Status | Valid |