Decree No. 16 / 2016 Coll.
Order on the conditions of connection to the electrical system
Valid
Effective from 01.02.2016
Zobrazeno prvních 200 z celkem 341 ustanovení tohoto předpisu.
Zobrazit celý předpis →
Pro stažení celého znění použijte tlačítko Stáhnout výše.
16
DECLARATION
of 13 January 2016
on the conditions for connection to the electricity system
Pursuant to Article 98a (2) (g) of Act No. 458 / 2000 Coll., on the Terms and Conditions of Business and on the Enforcement of State Administration in the Energy Sector and on the Amendment of Certain Laws (Energy Act), as amended by Act No. 211 / 2011 Coll., Act No. 382 / 2021 Coll., Act No. 469 / 2023 Coll., Act No. 87 / 2025 Coll. and Act No. 223 / 2025 Coll.:
Subject matter
This decree provides
(a) the conditions for the connection of power generating facilities (hereinafter referred to as the "production facility"), electricity storage facilities, distribution systems and demand facilities to the electricity system;
(b) how to determine the proportion of the costs associated with the connection; and
(c) the rules for assessing the simultaneous requirements for connection.
Basic provisions
For the purposes of this decree:
(a) reserved power
1. the value of the transmission-connected power input in MW in basic connection agreed with the transmission-connected system operator on the basis of the required power input and technical parameters of the transmission-connected system equipment; or
2. the value of the electrical input agreed with the distribution system operator on the basis of the required power input at the connection point in MW at a level of very high or high voltage or at the nominal current value of the main circuit breaker before the electrometer at A at the connection point at the low voltage level,
(b) the reserved power shall be the value of the electrical power agreed at the point of connection to the transmission or distribution system in MW;
(c) equipment for the production, storage, distribution or demand facility;
(d) by microdischarge of the power source and all associated electricity generation facilities, intended for parallel operation with a low voltage distribution system with a rated alternating phase current up to and including 16 A and a total maximum installed power up to and including 10,8 kW;
(e) by the applicant, a natural person, a natural person undertaking or a legal person requesting the connection of a transmission or distribution system installation or a change in the reserved power or power of an existing transmission or distribution system connected installation or a change in the nature of the procurement or change in the type or installed power of the power plant or electricity storage facility and who is entitled to use the installation on the basis of a right of ownership or otherwise; the applicant is also considered to be a natural person, a natural person undertaking or a legal person intending to build an installation in a given territory, and a natural person, a natural person undertaking or legal person applying for or amending the connection contract;
(f) the installed output of the production plant, the sum of the rated output of all generators; In the case of production plants using solar panels, the sum of the nominal power values of all installed solar panels;
(g) installed power of the electricity storage facility
1. the sum of the rated output power of the power electronics through which the electricity storage facility is connected to the transmission or distribution system; or
2. the sum of the nominal output of all generators that are part of a power storage facility where the power storage facility is not connected to the transmission or distribution system via power electronics.
Conditions for connection of an electrical system
(1) The conditions for connection of the applicant's equipment to the transmission or distribution system shall be:
(a) the request for connection;
(b) a study of the accessibility under the conditions set out in Sections 6 and 7; and
(c) the connection agreement between the applicant and the transmission system operator or distribution system operator or the modification of the existing connection contract (1).
(2) Paragraph 1 shall not apply and only the connection contract between the applicant and the transmission system operator or distribution system operator shall be a condition for connecting the transmission system operator or distribution system operator in the absence of a change in the technical conditions of connection with:
(a) the change of the licence holder operating the installation without interruption of the connection of the transmission system or distribution system;
(b) the replacement or modification of a power storage facility or plant where the existing contracted amount of the reserved power is not exceeded or the type of power storage plant or plant is changed or the installed power of the power storage plant or plant is increased while maintaining standard conditions for the transmission or distribution of electricity;
(c) a change of the natural or legal person authorised to use the collection electrical equipment; in the case of a customer whose installation is connected to the distribution system at low voltage voltage voltage, the requirements for the application for the conclusion of the connection contract are set out in Annex 5 to this Decree,
(d) reduction of the reserved power or power consumption of the installation;
(e) the change in customer identification data;
(f) connection in accordance with the procedure laid down in Article 16;
(g) installation of a replacement resource (7).
(3) The reserved power at the connection point of the installation directly connected to the electrical system or at the connection point of the installation through which another installation is connected may be agreed in the connection contract as a maximum of the total of the rated power, the sum of the rated power output of the power electronics through which the equipment is connected at the connection point and 1,2 times the sum of the rated power of the generators at the connection point not connected via the power electronics.
(4) The reserved power input of the transmission point at the voltage level of high voltage and higher may be negotiated in the connection contract in the range of the highest reserved power input from all the points of connection constituting the transfer point to the sum of the reserved power input of all the points of connection forming the transfer point. The reserve power of the transmission point at the voltage level of the low voltage is agreed in the connection contract according to the nominal current value of the main circuit breaker before the electrometer at the transmission point; In the case where the transfer point is not equipped with the main circuit breaker in front of the electrometer, the nominal current value of the nearest pressurised security element shall be used.
(1) The application for connection shall be submitted separately for each installation. Application for connection of equipment shall be submitted:
(a) prior to the construction or connection of a new installation, with the exception of the procedure laid down in Article 16;
(b) before changing the reserved power or power of an existing connected installation, except in the cases referred to in Article 3 (2);
(c) prior to the change in the nature of the sampling provided for in Annex 3 to this Decree,
(d) in the event of a change in the type of plant or plant for the storage of electricity or the replacement of a plant or plant for the storage of electricity by a plant or plant for the storage of electricity of the same type, except in the cases referred to in Article 3 (2) (b);
(e) in the event of a change in the connection point to the transmission or distribution system;
(f) in the event of an increase in the installed power of the plant or electricity storage facility connected to the distribution system.
(2) In the case of a power storage facility or plant with an installed power of more than 0,5 MW, the application for connection shall also include a timetable for the preparation of the construction of the power storage facility or plant containing the estimated dates.
(a) issuing a binding opinion on the impact of the implementation of the project on the environment, where required by law;
(b) the decision to authorise the project;
(c) start of construction of a power storage plant or plant;
(d) termination of the construction of a power storage plant or plant.
(3) The details of the application for the connection of each type of installation are set out in Annex 1 to this Decree.
(4) The application shall be made in paper or electronic form.
The production or storage facility may be connected at the customer's sampling point or via another already connected production or storage facility. The connection of the power storage facility or plant at the sampling point is requested and the connection contract is concluded by the customer. The connection of a power storage facility or plant through another power storage facility or plant shall be treated as the connection of a power storage facility or plant at the sampling point, with the application being submitted and the connection contract being concluded by the power storage facility manufacturer or operator whose power storage facility or plant is already directly connected to the transmission or distribution system.
(1) The transmission system operator or distribution system operator may require the applicant to process a study of the connectivity,
(a) if, taking into account all circumstances, it is clear that the installation for which the applicant requests connection will affect the operation of the transmission system or distribution system; or
(b) when the device is requested to be connected to a voltage level of high voltage and higher.
(2) Addability studies are not required in case of a reduction of the reserved power or power.
(3) Where an applicant requests a transmission system connection or an increase in the reserved power input or power at the connection point of the transmission system connection, the transmission system operator and the distribution system operator shall jointly ensure the processing of the connectivity study.
(4) The study of the connectivity of the plant, the storage facility or the demand facility shall assess the expected effects of the connection of the transmission system or distribution system. In addition, an assessment of possible variants of the required connection in terms of cost is the subject of a study of the connection of the transmission system or distribution system to another distribution system.
(5) The transmission system operator or distribution system operator may request the processing of a study of the connectivity within 30 days of the request for connection. At the same time, it must define the required extent of the study of connectivity.
(6) If the applicant requests the TSO or the distribution system operator to provide documentation for the processing of the addendum study no later than 30 days after receipt of the request for processing, the TSO or the distribution system operator shall provide the applicant with the necessary documentation for the processing of the attachment study within 15 days of their request. If the applicant does not request the transmission system operator or distribution system operator to provide documentation for the processing of the addendum study within 30 days of receipt of the request for processing, the transmission system operator or distribution system operator shall not consider the connection request.
(7) Where the transmission system operator or distribution system operator does not request the processing of the appendability study within the time limit referred to in paragraph 5 or does not provide the applicant with the necessary documentation for the processing of the appendability study, it shall be deemed not to require the processing of the appendability study.
(8) The applicant for connection to the distribution system shall submit to the distribution system operator a study of the connectivity within 90 days of the date on which the distribution system operator transmitted to the applicant the documentation necessary for the processing of the study, unless otherwise agreed between the applicant and the distribution system operator. Where an applicant requests a connection to a transmission system, the applicant shall transmit to the transmission system operator a study of the connectivity within 180 days of the date on which the transmission system operator transmitted to the applicant the documentation necessary for the processing of the study, unless otherwise agreed between the applicant and the transmission system operator.
(1) In the absence of an attachment study to the extent defined by the transmission system operator or distribution system operator, the transmission system operator or distribution system operator may request its completion or extension. The transmission system operator or distribution system operator may request the addition or extension of the appendability study no later than 30 days after the transmission of the appendability study. Where the TSO or the distribution system operator does not request the addition or extension of the appendicibility study within that period, it shall be deemed not to require the addition or extension of the appendability study.
(2) If the TSO requests the addition or extension of the appendicibility study, the applicant shall transmit the additional or extended appendicibility study within 90 days of receipt of the request by the TSO, unless otherwise assessed.
(3) Where the distribution system operator requests the addition or extension of the appendicibility study, the applicant shall transmit the additional or extended appendicibility study within 30 days of receipt of the request by the distribution system operator, unless otherwise assessed.
(1) The transmission system operator or distribution system operator shall assess the application for the connection of the installation with regard to:
(a) the location and manner of the required connection;
(b) the size of the required reserved power or power and the time course of load;
(c) reliability of electricity supply;
(d) the nature of the reactivity of the applicant's equipment on the transmission or distribution system;
(e) planned system development and the economy of system development and operation;
(f) the order of the applications submitted,
(g) the connection power limits to the electricity system established by the TSO;
(h) the size of the installed power of the plant and the installed power of the electricity storage facility; and
(i) the obligation to connect the production from the supported source to the transmission or distribution system as a priority under the Energy Support Act (2).
(2) Where necessary for an appropriate assessment of the connection request, the TSO or the distribution system operator shall invite the applicant no later than 15 days from the date of receipt of the request to supplement the data provided to the extent necessary and shall set a reasonable deadline. At the same time, the applicant shall indicate that the application will not be considered if the data to the extent requested are not completed.
(3) Where the applicant has been requested to supplement the data provided pursuant to paragraph 2 and the applicant has not done so, the TSO or distribution system operator shall not assess the request. It shall communicate this to the applicant without undue delay.
(4) If the reasons set out in the Energy Act for which the transmission system or distribution system operator cannot be connected (3) are not provided, the distribution system operator shall submit to the applicant within 30 days or, in the case of an installation connected to a voltage level of high or very high voltage within 60 days of the submission of a complete request for connection or from the date of transmission of the study of the appendability, a draft connection contract or a draft future connection contract. In the case of an installation connected to a transmission system, the time limit for the submission of a draft connection agreement or contract shall be 90 days from the date of submission of the complete request for connection or the date of transmission of the study to the connection if the study was requested to be processed.
(5) If the installation of the applicant cannot be connected for reasons specified by the power-generating facility), the transmission system operator or distribution system operator shall inform the applicant in writing of this fact in the case of an installation connected to the voltage level of the low voltage within 30 days, or in the case of an installation connected to the transmission system within 60 days, or in the case of a plant connected to the transmission system within 90 days of the submission of a complete request for connection or from the date of transmission of the study, where the processing of the study was requested. At the same time, the transmission system operator or distribution system operator shall state the specific reasons for which the applicant's equipment cannot be connected and shall indicate the provisional deadline and the preconditions for future connection.
(6) Where, in the case referred to in paragraph 5, the applicant may be connected by:
(a) under other conditions,
(b) less than the required power or power; or
(c) ensuring that the technical equipment of the generation or storage facility for the transmission of data and the restriction of active power supply by the transmission system operator or distribution system operator can be restricted to the use of the reserved power without compensation for such restriction when preventing or addressing overloads in the system (8);
the transmission system operator or distribution system operator shall inform the applicant in writing, at the same time as the reasons referred to in paragraph 5 for which the installation cannot be connected under the required conditions, within the time limit referred to in paragraph 5; the transmission system operator or distribution system operator shall communicate all possible connections referred to in points (a), (b) or (c) where the applicant's facilities can be connected in such a way.
(7) If, within 20 days of the communication by the TSO or distribution system operator referred to in paragraph 6, the applicant confirms in writing one of the possible connections referred to in paragraph 6 (a), (b) or (c), the TSO shall submit a draft contract to the applicant within 25 working days or the distribution system operator shall submit a draft contract within 15 working days; where it is possible to connect applicants at multiple connection points, they shall submit a draft contract only if the applicant confirms the connection at one of those connection points within 20 days of the communication of the transmission system operator or distribution system operator.
(8) If the measurement or verification of network operation is necessary for the assessment of the application for connection by calculation, the deadline referred to in paragraphs 4 to 7 and Article 6 (5) shall be extended by the time needed for the measurement or verification of network operation, but not more than 30 days at a level of very high voltage and especially high voltage and by 15 days at high voltage and low voltage. The transmission system operator or distribution system operator shall inform the applicant of the necessity of measuring or verifying the operation of the network and of the extension of the deadline within 15 days of the date of receipt of the complete request for connection at the latest.
(1) The transmission system operator or distribution system operator shall determine the connection point, the connection method, including the determination of the voltage level, the connection date and other connection conditions, so that the specified connection conditions are based on the connection request, the planned network development and the principle of the development and operation of the system, taking into account the applicant's interest in minimising the costs of connecting the transmission system or distribution system.
(2) The transmission system operator or distribution system operator shall reserve the requested power or power from the time of submission of the draft contract in accordance with Paragraph 8 (4).
(3) If the applicant does not accept a draft contract within 30 days for connection to a low voltage voltage voltage voltage level or within 60 days for connection to a high voltage voltage voltage level and above from the date of submission of the draft contract by the TSO or the distribution system, the reserve power or reserve power shall cease.
(4) In the case of a requirement under Paragraph 3 (2) (c), the distribution system operator shall submit a draft connection contract to the applicant within 10 days of the date of receipt of the request; the absence of a statement by the original customer showing that it has ceased to use the demand facility is not a reason to reject the requirement under Paragraph 3 (2) (c), provided that, according to Annex 5 to this decree, an affidavit is supported that the original customer is not known to the applicant.
(1) If the installation has not been connected for reasons specified by the Energy Act) and these reasons have ceased, the transmission system operator or distribution system operator shall communicate this fact to the applicant to whom it has communicated the facts referred to in Article 8 (5) in the previous 5 years.
(2) If the reasons for the connection of an installation pursuant to Article 8 (6) (b) or (c) have ceased, the transmission system operator or distribution system operator shall communicate this to the person with whom the connection agreement has been concluded in the previous 5 years on the basis of the submitted proposal pursuant to Article 8 (7).
(3) The communication referred to in paragraphs 1 to 3 shall not be provided by the distribution system operator, if the interactive map 9 is published) on the free distribution capacity for a voltage level of very high and high voltage and the free capacity of electrical stations or free capacity at a specific demand point at a voltage level of low voltage in the distribution system operated by it.
(1) In the event of termination of a transmission system service contract or of a distribution system service, the reserve of power for the existing connection point shall last for 48 months from the date of termination of the contract obligation. If a contract for the provision of a transmission system service or the provision of a distribution system service has not been concluded for the connection point within 48 months of the date of the connection agreed in the connection agreement, the reservation of power at the connection point shall cease.
(2) In the case of an application pursuant to Article 4 (1) (d), the transmission system operator or distribution system operator shall reserve for the applicant the most recently agreed amount of the reserved power at the existing connection point until the date of submission of the draft contract pursuant to Article 8 (4), but for a maximum period of 24 months from the submission of the request pursuant to Article 4 (1) (d), otherwise the reservation of power at the existing connection point shall cease.
Method for determining the proportion of eligible costs
(1) Where the applicant is covered in full by this Order, only the costs referred to in paragraphs 2 and 3 may be included in the costs borne by the applicant.
(2) The costs associated with the connection shall include the strictly necessary legitimate costs incurred in connection with the acquisition, construction or modification of the transmission system or distribution system, which have been triggered by the applicant's request in relation to the location and the way in which its equipment is connected. The acquisition, construction or modification of a transmission system or distribution system shall be provided to the extent necessary to the corresponding value of the power or power required by the applicant and the location and connection of its equipment.
(3) The cost of acquiring project documentation, geodetic orientation and other directly related investment costs, including costs directly related to the acquisition of the service, and the reimbursement of the price associated with the construction, modification or acquisition of the transmission system or distribution system, shall be included in the costs associated with the connection.
(4) The costs associated with the connection shall not include costs related to the acquisition, construction or modification of the transmission system or distribution system, which, by their scope, exceed the necessary level of power or power required by the applicant and the location and connection of its equipment.
(5) The construction and modification of the transmission system is defined from the point of connection of the applicant's installation to the nearest point in the transmission system where the required reserved power or power is or would be available after making the necessary adjustments in the system.
(6) The construction and modification of the distribution system is defined from the point of connection of the applicant's equipment to the nearest point in the distribution system at the same voltage level where the required reserved power or power is or would be available after making the necessary adjustments in the system.
(1) The flat-rate amount to cover the costs associated with the connection of the installation (hereinafter referred to as the "proportion of eligible costs") shall be calculated as the product of the specific proportion referred to in Annex 2 to this Order and by the applicant of the requested reserved power or power.
(2) In the case of connection of a power-generating facility or power-generating facility to a transmission or distribution system, the supply line shall be fully reimbursed by the applicant to the connection point.
(3) If a power reservation is simultaneously requested for one applicant at a single connection point, the share of the eligible costs shall be determined separately for the power reservation and for the performance reservation. The applicant shall pay a higher of the two agreed share of the eligible costs.
(4) Where the applicant at the existing site of connection of the installation requests a reservation of power or power, even at the same time, the applicant shall, if the proportion of the eligible costs for the total increased reserved power or power
(a) is less than or equal to the value of the higher of the eligible cost shares fixed for the current power or exercise under this Order, does not cover the proportion of eligible costs;
(b) it has a higher value than the value of the higher of the shares in the eligible costs fixed for the current input or execution under this decree, the share in the eligible costs shall be paid only to the extent that the difference between the higher share in the eligible costs for the total increase in the reserved charge or performance and the higher share in the eligible costs established for the existing input or performance under this decree is met.
(5) The share of eligible costs shall not be applied in the cases referred to in Article 3 (2). This does not apply if the time of booking of power according to § 10 has expired.
(6) On the basis of the contract, the applicant shall pay an advance on the share of the eligible costs referred to in Annex 2 to this decree, at the rate of 50% of the value of the share of the eligible costs, but not more than CZK 50 000 000. The applicant shall pay an advance on the share of the eligible costs within 15 days of the date of conclusion of the connection contract or future connection contract.
(7) Where the transmission system operator or distribution system operator has incurred costs related to the modification of the transmission system or distribution system due to a change in the type of production or storage facility referred to in Article 4 (1) (d), the applicant shall pay the full cost. The share in the eligible costs under this paragraph shall not be paid for the amount of the required performance at the existing connection point which does not exceed the last agreed amount of the reserved performance at the existing connection point.
(8) If the device is requested to be connected to high voltage voltage voltage and higher, the non-refundable share of the eligible cost is 30% of the value of the share in the eligible costs, but not more than CZK 50 000 000, if the reservation of performance or power at the time of its demise lasted less than 12 months, otherwise 50% of the value of the share in eligible costs, but not more than CZK 50 000 000. If the device is requested to be connected to the low voltage voltage voltage voltage level, the non-refundable portion of the eligible cost share is 0% of the value of the eligible cost share.
Conditions for connection of an electrical system above standard connections
(1) Where an applicant requests the connection of an installation in excess of the standard connection, in particular where he requests a specific method of the construction or technical design of the connection of a transmission system or distribution system, the applicant shall bear the legitimate costs associated with the implementation of the superstandard connection or the specific construction or technical design of the connection in full.
(2) The reserve power or power may only be transferred if technically possible and the execution of the transfer of the reserved power or power does not entail additional costs related to the acquisition, construction or modification of the transmission or distribution system.
(3) The transfer referred to in paragraph 2 may take place:
(a) on a low voltage level only between the points of connection of equipment connected from one transformer with a high voltage to low voltage transformation;
(b) on a high voltage level only between the points of connection of equipment connected from one transformer with a transformation from a very high voltage to a high voltage;
(c) at a very high voltage level only between the connection points of the equipment connected from one node station providing connection between the transmission system and the distribution system;
(d) in the transmission system, only between the connection points of equipment connected from one electrical station and, in the case of distribution systems, between the connection points of distribution systems within a single node area.
(4) Only reserved power or power of already connected equipment may be used to transfer the reserved power or power referred to in paragraphs 2 and 3. Paragraph 10 shall not apply.
(5) If the applicant requests to be connected to a voltage level other than that to which the device is connected and the requested change in connection is not required by a change in the technical conditions of the connection, the applicant shall bear the full costs associated with the change. In such a case, a share of the eligible costs pursuant to § 12 shall not be reimbursed up to the amount of the original reserved power or power. Paragraph 10 shall not apply.
Where the transmission system operator or distribution system operator attaches a customer's demand facility to which the supply of electricity has been restricted or interrupted due to the unauthorised collection, transmission or distribution of electricity, the customer shall pay a share of the eligible costs of:
a) CZK 1,500 when connected to low voltage voltage voltage,
b) CZK 3,500 when connected to high voltage voltage voltage or higher.
(1) Short term connection means the connection of a provisional device
(a) construction sites and demolitions;
(b) at exhibitions and cultural events,
(c) temporary buildings and stands; and
(d) for making films and television broadcasts
to a fixed-term distribution system. In the short term, neither production nor electricity storage facilities can be connected to the distribution system.
(2) In the case of short-term connection, the applicant shall submit a request for short-term connection to the distribution system separately for each installation. The details of the applicant's application for short-term connection are set out in Annex 1 to this Decree.
(3) Paragraph 4 to 10 shall apply mutatis mutandis to short-term connections. The location of the connection shall preferably be determined in such a way as to avoid the need for the costs of the connected distribution system operator.
(4) Where the distribution system operator incurs costs related to ensuring the short-term connection of the applicant's equipment, the applicant for short-term connection to the distribution system shall pay the costs associated with the connection, including the cost of putting the connection point at the end of the withdrawal in full. The share of the eligible costs referred to in Article 12 shall not be reimbursed.
(5) On termination of the fixed-term connection contract, the reserve of power shall cease; Article 10 shall not apply.
(6) If, due to the implementation of short-term connection to the distribution system, there is a need for an increase in the reserved power input at the connection points between the distribution system at which the short-term connection took place and another distribution system, the procedure shall be followed in accordance with paragraph 4.
Conditions for simplified connection to the distribution system
(1) The simplified connection can connect a microconductor or a power storage device with an installed power up to 10,8 kW on a low voltage level. The sum of the installed power of all micro-units and electricity storage facilities connected at the sampling point by the simplified connection shall not exceed 10,8 kW.
(2) The conditions for connection of microgrid or power storage facilities with installed power up to 10,8 kW of the applicant to the distribution system are:
(a) the measured value of impedance at the point of connection to the distribution system which is not greater than the value of the limit impedance referred to in paragraph 3;
(b) a technical solution for the microgrid or an installation for the storage of electricity with an installed power of up to 10,8 kW which prevents the supply of electricity to the grid at the connection point, except for short-term overflows of electricity to the distribution system, which are used for the response of the limiting device but which does not increase the value of the voltage at the connection point;
(c) the submission of an application for the conclusion of a connection contract or an amendment to an existing connection contract in accordance with Annex 4 thereto; and
(d) the conclusion of a connection agreement between an applicant for a micro-grid connection or an installed power storage facility of up to 10,8 kW and a distribution system operator or an amendment to an existing connection contract (1), the reserved power being zero.
(3) Where the sum of the installed power of microdroplets and power storage devices with an installed power of up to 10,8 kW connected at one sampling point exceeds 800 W, the applicant shall ensure that the impedance of the current loop at the point of connection to the distribution system is measured by a person with competence (6). The technical conditions for measuring impedance shall be deemed to be met if they comply with the harmonised technical standard governing the measurement of impedance. The value of the limit impedance is for sources up to 16 A for phase 0,47, and for resources up to 10 A for phase 0,75. Where the measured value of impedance is greater than or equal to the limit impedance value, the applicant may connect a micro-unit or a power storage facility with an installed power up to 10,8 kW at the sampling point only under the conditions laid down in Article 3 (1).
(4) The applicant shall submit an application for a connection contract or an amendment to an existing connection contract to the distribution system operator with which it has a connection contract. The elements of the application for the conclusion of the connection contract under the simplified scheme are set out in Annex 4 to this decree. The application shall include the consent of the owner of the property to the location of the micro-device or the installation of a power storage facility with installed power up to 10,8 kW on its property.
(5) The distribution system operator shall assess the completeness of the data contained in the request referred to in paragraph 4 no later than 15 days after the submission of the request. If the data are incomplete or in accordance with the requirements of points (a) to (c) of paragraph 2, the distribution system operator shall invite the applicant no later than 15 days from the date of receipt of the request to supplement the data to the extent necessary and shall set a reasonable time limit. At the same time, the applicant shall indicate that the application will not be considered if the data to the extent requested are not completed. Otherwise, it shall send the applicant a draft connection contract no later than 20 days after receipt of the complete application for the connection contract.
Common provisions
(1) The length of the electrical connection is the length of the shortest construction and technically feasible route of the connection projected into the ground plan between the point of departure from the distribution system and the main house fuse or main home cable box.
(2) A vertical part of the electrical connection shall not be counted.
Transitional provision
The application for connection, the request for conclusion of the connection contract or the request for amendment of the connection agreement submitted before the date of application of this decree shall be assessed in accordance with the existing legislation.
Repeal
The following shall be deleted:
1. Decree No. 51 / 2006 Coll., on the conditions of connection to the electricity system.
2. Decree No. 81 / 2010 Coll., amending Decree No. 51 / 2006 Coll., on Conditions of Connection to the Electricity System.
Efficacy
This Decision shall enter into force on 1 February 2016.
President:
Ing. Vitásková v. r.
Příloha č. 1
Annex No 1
OBLIGATIONS OF THE REQUEST FOR THE APPROACH TO THE TRANSPORT OR DISTRIBUTION SYSTEM
1. Business company (completed by the applicant - entrepreneur registered in the Commercial Register).
2. Data on registration in the Commercial Register, including the file tag (completed by the applicant - entrepreneur registered in the Commercial Register).
3. Name or surname (completed by the applicant not registered in the Commercial Register).
4. Date of birth (completed by the applicant - natural person).
5. Location broken down: State, county, municipality, street and descriptive number, or registration number (completed by the applicant - legal person or natural person undertaking).
Sign in for notes, favorites and notifications
Regulation Information
| Citation | Decree No. 16 / 2016 Coll., on the Conditions of Connection to the Electricity System |
|---|---|
| Regulation Type | - |
| Author | - |
| Collection | Code of Laws |
| Date of Promulgation | 22.01.2016 |
|---|---|
| Effective from | 01.02.2016 |
| Effective until | - |
| Status | Valid |
The regulation text is for informational purposes only.
Comments 0