Decree of the State Planning Commission No. 92 / 1967 Coll.
Decree of the State Planning Commission on fuel and energy bases for solid, liquid or gaseous fuel and electricity appliances
Valid
Effective from 01.10.1967
92
DECLARATION
State Planning Commission
of 25 August 1967
on fuel and energy bases for appliances for solid, liquid or gaseous fuels and electricity
In agreement with the ministries of mining, chemical industry, heavy industry, Central Energy Administration and other participating central authorities, the State Planning Commission provides, pursuant to § 391 (1) of Economic Code No. 109 / 1964 Coll.:
Consumers of solid, liquid or gaseous fuels and electricity covered by this Decree (hereinafter referred to as appliances) are:
(a) heat plants for central heating and industrial boilers in which solid, liquid or gaseous fuels are burned if the nominal output of the total heat source (e.g. the whole boiler room) is at least 600,000 kcal / hour; if it is a gas combustion plant, only if the annual consumption of the lamp or coke oven gas exceeds 600,000 m3 / year and the natural gas exceeds 300,000 m3 / year;
(b) other plants in which solid, liquid or gaseous fuels are burned if the performance of individual fuel plants is at least 300,000 kcal / h for solid or liquid fuel appliances and 150,000 kcal / h for heating gas appliances, if, for all newly connected gas appliances, the annual consumption of light or coke oven gas exceeds 600,000 m3 / year and natural gas exceeds 300,000 m3 / year;
(c) installations where electricity is used for direct heating of industrial furnaces and drying plants, if their electrical output is at least 1000 kW;
(d) equipment in which solid, liquid or gaseous fuels are processed as raw materials.
(1) For each newly built or reconstructed appliance for which any of the conditions referred to in Section 1 is met after completion of construction or reconstruction, a fuel or energy base shall be determined. It shall be determined by agreement between the investor (customer) and the fuel or energy supplier, *) in accordance with the process of working on the project documentation; at the stage of the preparatory project work, where appropriate in the form of a pre-commitment with an agreed time-period.
(2) The agreement or provisional commitment on a fuel or energy base shall include in particular:
(a) the name and registered office of the organisation with a closer indication of the operating unit in which the appliances will be built or reconstructed, and a list of such appliances, including their parameters, indicating whether new or reconstructed;
(b) the total annual fuel or energy needs in actual units, including quality characteristics according to the applicable CSN, supplemented on request by the investor (customer) by additional (e.g. for solid fuels with combustion heat, quality characteristics of ash and sulphur content) and annual need in each year until full (planned) use of the capacity of appliances; where gas or electricity are involved, whether or not the maximum and average hourly delivery and annual use of the maximum;
(c) the name and registered office and, where appropriate, the name of the operating unit of the relevant fuel or energy supplier;
(d) the technical conditions for the implementation of the fuel or energy base;
(e) as regards the fuel or energy base agreement, also the relationship between the customer and the supplier, relating to the collection and supply of fuel or energy, in particular the property consequences of failure to comply with the agreement and the conditions under which one or other party is entitled to withdraw from the agreement.
Before concluding an agreement on a fuel or power base for which the annual need for the full use of appliances is at least
| 100 tis. tmp | pevných paliv |
| 7 tis. tun | topných olejů |
| 7 tis. tun | benzínu (pro přímý ohřev a plynárenské účely) |
| 7 mil. m3 | zemního plynu |
| 15 mil. m3 | svítiplynu |
| 20 mil. m3 | koksárenského plynu |
| 5 tis. tun | topného plynu propan-butan |
| 3 mil. kWh | elektřiny (pro přímý ohřev průmyslových pecí a sušáren), |
assess its determination from the perspective of the perspective of a comprehensive approach to covering the needs of the national fuel and energy economy by the State Planning Commission on the basis of the opinion of the central body of the customer and supplier as regards organisations in Slovakia, as well as the Slovak Planning Commission. This applies even if the customer and supplier are the same organisation and determine their own fuel or energy base. The supplier requests the assessment in agreement with the customer. The opinion of the State Planning Commission (from the point of view of concluding agreements within the meaning of Paragraph 2) * * *) is binding on customers and suppliers of fuels or energy.
Fuel and electricity suppliers are obliged to inform The State Planning Commission (including the Slovak Planning Commission) on the determination of all fuel or energy bases on which investors (customers) agreed with them in preparation for the construction or reconstruction of appliances or their changes. This obligation shall also apply where the supplier and the customer are the same organisation and determine their own fuel or energy base.
(1) The Decree of the State Planning Commission No 112 / 1961 Coll., on the determination of fuel bases for appliances of solid, liquid or gaseous fuels, is repealed. Decisions to determine fuel bases issued pursuant to it shall remain in force.
(2) This Decree shall take effect on 1 October 1967.
Chairman:
v. z. Dvořák v. r.
*) Fuel and energy suppliers are:
| Sdružení výrobců paliv (dříve Uhlozbyt) Praha | — černé a hnědé uhlí včetně meziproduktu lignit, koks; |
| Čs. plynárenské podniky, oborové ředitelství | — zemní plyn, svítiplyn, koksárenský plyn, topný plyn, propan-butan; |
| Hutnictví železa, oborové ředitelství | — koks a koksárenský plyn, vyprodukovaný v hutních koksovnách, vysokopecní plyn; |
| Chemopetrol — Závody pro zpracování ropy, oborové ředitelství | — topné oleje, benzín pro technologické účely, hnědouhelný koks, topný plyn propan-butan; |
| Krajské energetické podniky, a jde-li o dodávku z nadřazené soustavy, Čs. energetické závody — generální ředitelství | — elektrická energie, je-li používána jako topné medium pro průmyslové pece a sušárny; |
| a jimi pověřené organizace, nebo i jiné organizace, které vyrábějí a dodávají palivo nebo elektrickou energii. | |
* *) The State Planning Commission shall address the draft agreement no later than 60 days after its submission.
Sign in for notes, favorites and notifications
Regulation Information
| Citation | Decree of the State Planning Commission No. 92 / 1967 Coll., on fuel and energy bases for appliances of solid, liquid or gaseous fuels and electricity |
|---|---|
| Regulation Type | - |
| Author | - |
| Collection | Code of Laws |
| Date of Promulgation | 26.09.1967 |
|---|---|
| Effective from | 01.10.1967 |
| Effective until | - |
| Status | Valid |
The regulation text is for informational purposes only.
Comments 0