Decree of the Ministry of Industry and Trade No. 251 / 2001 Coll.

Decree of the Ministry of Industry and Trade laying down rules on the operation of transmission and distribution systems in the gas industry

Valid Order Effective from 24.07.2001
251
DECLARATION
Ministry of Industry and Trade
of 27 June 2001
laying down rules on the operation of the transmission and distribution systems in the gas industry
The Ministry of Industry and Trade (hereinafter referred to as "the Ministry") provides, pursuant to § 98 (7) of Act No. 458 / 2000 Coll., on the terms of business and on the exercise of state administration in the energy sector and on the amendment of certain laws, (hereinafter referred to as "the Act") for the implementation of § 57 (1) (a), § 58 (1) (a), § 58 (8) (d), § 59 (1) (b), § 62 (2) (b), § 71 (3), § 71 (11) and § 74 (2):
§ 1
Basic provisions
(1) For the purposes of this Decree, a transfer point shall mean a place allowing the measurement of the quantity and, where applicable, the pressure of the gas transported and supplied, the regulation of gas flow, the measurement of the gas quality for the purpose of calculating its supply in kWh or MWh (hereinafter referred to as "energy units') and the transfer of data to dispatches. The transfer point shall be established:
(a) between the transmission system and the distribution system;
(b) between the transmission system and the production gas;
(c) between the transmission system and the underground gas container;
(d) between the transmission system and the direct pipeline;
(e) between two distribution systems,
(f) between the distribution system and the production gas;
(g) between the distribution system and the underground gas container;
(h) final customers.
(2) For the purposes of this decree, a transfer point shall be the point referred to in paragraph 1 (a) to (d).
(3) The quality of the gas for the calculation of the gas supply in the energy units is to be collected in the gas system at locations determined by the transmission system operator and distribution system operators.
(4) At border transmission stations and at outputs from the gas production plant or from the underground gas storage tank to the transmission or distribution system, both the quantity and the quality of the gas shall be measured.
(5) Individual gas system facilities are divided by dividing points. The point of division of the downstream gas installations of each licence holder shall be the input or output side of the main closing fittings at the point of entry into or exit from the point of transfer. This input or output side is the flanging plane or axis of the connection weld in the field and in the relevant documentation marked with fittings, stored with both connecting system operators or gas installations. These dividing points are
(a) for the gas plant:
1. the output side of the main closing fittings at the output from the manufacturer's transmission station;
2. the output side of the main closing fittings on the connection pipe,
(b) for the transmission system:
1. place of the pipeline crossing across the state border of the Czech Republic,
2. the output side of the main closing fittings at the output from transmission stations operated by the transmission system operator;
3. the input side of the main closing fittings at the entrance to the transmission stations operated by the distribution system operator, the underground gas storage tank, the direct pipeline or the customer holding the transmission station;
(c) for distribution systems
1. the output side of the main closing fittings at the output from transmission stations operated by the transmission system operator and used for connecting the distribution system;
2. the input side of the main closing fittings at the input to transmission stations operated by the distribution system operator and used for connecting the distribution system to the transmission system;
3. the output side of the main closing fittings at the outlet of the transmission points operated by the distribution system operator and used for connecting another distribution system;
4. the input side of the main closing fittings at the entrance to the transfer points operated by the customer;
5. the input side of the main closing fittings at the input to the gas supply connection or the input side of the main closing fittings of the sampling gas installation;
(d) in the case of an underground gas container,
1. the input side of the main closing fittings at the inlet to the gas transfer station and the output side of the main closing fittings of the gas storage tank. In the case of one transfer station with the possibility to work in both modes, the input and output sides of the main closing fittings are identical,
2. the input side of the main shut-off gas pipeline, connecting the underground container to the transfer system for insertion and the output side of the main shut-off gas pipeline, connecting the container to the gas extraction system.
(6) The quantity of gas delivered and collected shall be evaluated as the quantity of energy expressed in energy units by converting the quantity of gas in m3 into energy according to the principles of conversion of volume units of energy quantities set out in Annex 1.
(7) In determining the gas volume in m3, the GCV in kWh / m3 and Wobbe numbers in kWh / m3, the following conditions apply:
(a) temperature 15 ° C,
b) a pressure of 101,325 kPa;
(c) burning temperature 15 ° C;
(d) the relative humidity of the dry gas shall be as follows:
§ 4
Conditions for ensuring the transport of gas
(1) The gas transport by the transmission system is ensured by a contract concluded to ensure the transport of gas.
(2) The conditions for the transport of gas are:
(a) the spare capacity of the transmission system;
(b) compliance with transfer pressures;
(c) compliance with the gas quality.
(3) The spare capacity of the transmission system is the difference between the actual capacity of the transmission system or its individual parts and the sum of all capacities contracted for each customer within a given time period, while respecting contractual pressures.
(4) In order to ensure the transport of gas through border transmission stations of the transmission system pipeline, the contractual pressures determined by the transmission system operator shall be respected at the entry into the transmission system and the maximum pressure up to the operating pressure at the connection point and the minimum pressure agreed in the contract shall be respected at the exit from the transmission system.
(5) In order to ensure the transport of gas, the maximum transmission pressure up to the nominal pressure at the connection point and the minimum operating pressure at the connection point shall be respected at the entry into the transmission system. The output of the transmission system shall comply with the maximum pressure up to the operating pressure at the connection point and the minimum pressure agreed in the contract.
(6) The request to ensure the transport of gas shall be submitted to the transmission system operator on the form prescribed by him no later than 3 months before the date of the start of the transport of the gas.
(7) The transmission system operator shall issue a written opinion on the request for gas transmission within 30 days of the date of receipt of the request, which shall be justified in the event of disagreement. In case of consent, it shall send the applicant a draft contract to ensure the transport of gas.
(8) If the request to ensure the transport of gas relates to the transport of gas through the Czech Republic, the Ministry shall be informed of the outcome of the negotiations.
§ 5
Conditions for ensuring gas distribution
(1) The distribution of gas by the distribution system is ensured by a contract concluded to ensure the distribution of gas.
(2) The conditions for ensuring distribution of gas by the distribution system are:
(a) the spare capacity of the distribution system;
(b) compliance with transfer pressures;
(c) compliance with the gas quality.
(3) The spare capacity of the distribution system is the difference between the actual capacity of the distribution system or its individual parts and the sum of all capacities contracted for each customer over a given period of time, respecting contractual pressures.
(4) In order to ensure gas distribution, the maximum transmission pressure up to the rated pressure at the connection point and the minimum operating pressure at the connection point shall be respected at the entry into the relevant distribution system. The output from the relevant distribution system shall comply with the maximum pressure up to the operating pressure at the connection point and the minimum pressure agreed in the contract.
(5) The request to ensure the distribution of gas shall be submitted to the distribution system operator on the form prescribed by him no later than 3 months before the date of the start of distribution.
(6) The gas distribution application shall be submitted by the relevant distribution system operator within 30 days of the date of receipt of the request in writing, which shall be justified in the event of disagreement. In the event of consent, it shall send the applicant a draft gas distribution contract.
§ 6
Gas supply conditions
(1) The supply of gas takes place on the basis of a contract concluded in writing for the supply of gas.
(2) The request for the supply of gas shall be submitted to the relevant gas operator or gas dealer on the form prescribed by him. The request shall not be made by the protected customer to whom a draft gas supply contract has already been sent pursuant to Paragraph 3 (9).
(3) The request for the supply of gas contains:
(a) identification details of the applicant;
(b) information on the extent and nature of gas consumption, including the time of delivery.
(4) The request for gas supply shall be accompanied by:
(a) a copy of the relevant gas business licence of the natural gas operator;
(b) a valid revision report and the technical documentation of the connected gas or gas demand facility at the final customer;
(c) proof of payment of the agreed advance of the share of the protected customer in the cost effectively incurred by the distribution system operator associated with the connection and the provision of the required supply;
(d) proof of operation and maintenance in the event of the connection of the final customer holding the pipeline connection.
(5) Measurement of the quantity of gas collected shall be carried out by measuring devices approved under a specific legislation. 1) The deduction of the quantity of gas collected shall be carried out at intervals determined by the operator of the relevant system but at least every 18 months and at the end of the contractual relationship.
(6) If the final customer does not allow access to the measuring equipment at the time of deduction of the quantity of gas collected and does not provide data on the measured amount of gas to the operator of the relevant system within 3 days of the date of deduction, the gas consumption shall be calculated as set out in Annex 2.
(7) If the quantity of gas actually collected cannot be determined due to the failure of the measuring equipment, the quantity of gas collected shall be calculated on the basis of the quantity of gas delivered during the same period of the last year. If consumption cannot be determined in this way, the quantity of gas delivered shall be determined retrospectively by subtracting the quantity of gas obtained in the following comparable period. This method of calculating the amount of gas collected is used only for final customers with an annual or 18-month deduction period. For other final customers and gas undertakings, the quantity of gas delivered shall be calculated in a manner agreed in the gas supply contract.
§ 7
Transmission stations
(1) Transmission stations shall be equipped with at least:
(a) the main and back-up measurement of the quantity of gas supplied with the evaluation and the possibility of conversion into energy transmitted on the basis of gas quality data obtained either directly at the transmission station or at the gas quality monitoring site; the measuring equipment shall be dimensioned according to the flow curve, sampling seasonality and minimum gas flow;
(b) the main closing fittings at the entrance and exit of the transmission station.
(2) If the transmission station is equipped with a gas quality measuring device, a minimum measurement shall be carried out
(a) the composition of the gas for the calculation of GCV, density and Wobbe number;
(b) dew point of water and hydrocarbons;
(c) sulphur and sulphur compounds content at border transfer stations.
(3) Transmission stations with installed power of 50 000 m3 / hour and more must be equipped with:
(a) gas flow control fittings;
(b) by remote control of the closing fittings located in front of the measuring equipment and the gas flow control fittings of the transmission system operator or distribution system operators concerned.
(4) The transmission stations at the points of connection of the underground gas storage device to the transmission or distribution system concerned shall be equipped with a separate measurement of the quantity and quality of the gas injected and extracted.
(5) Records of quantities, quality and transfer pressures of gas are made at least:
(a) once per hour for transmission stations with installed output of 10,000 m3 / hour or more;
(b) four times a day for transmission stations with installed power from 1 000 to 10 000 m3 / hour;
(c) once a day for transmission stations with installed power not exceeding 1000 m3 / hour;
(d) immediately upon failure of the technical equipment of the transmission station.
(6) Data on quantities, quality and transfer pressures of gas must be transmitted immediately after their entry to the dispatches of the relevant gas undertakings.
(7) Records of the quantity, quality and transfer pressure of gas referred to in paragraph 5 shall be kept for a minimum period of 3 months and the average daily data values referred to in paragraph 5 (a) to (c) for a minimum period of 3 years.
§ 8
Method of calculating the damage caused by unauthorised gas collection
(1) The daily quantity of gas unduly collected shall be calculated by multiplying the sum of the nominal consumption of all appliances of the final customer by the period of use set out in Annex 3.
(2) The total unauthorised gas consumption is the product of the daily quantity of gas unduly collected and the number of days for which the unauthorised gas was taken. If it is not possible to determine the number of days of unauthorised gas collection, the total unauthorised gas collection shall be determined over the period from the last deduction.
(3) The gas price and, where applicable, the price for distribution or transport of gas shall be used to calculate the compensation for the damage caused by the unauthorised gas collection, provided that they are set or charged separately, at the level of the maximum prices applicable during the period of illegal gas collection as decided by the price authority (2), for the relevant annual gas extraction, corresponding to the gas collection facility. In other cases, the price normally applied by the supplier in the same period of unauthorised gas collection shall be used for a comparable case of contractually authorised gas collection.
§ 9
Transitional provision
Paragraphs 2 (5) and 3 (5) may apply from 1 January 2005.
§ 10
Repeal
They shall be deleted:
1. Decree No. 196 / 1995 Coll., which sets out in more detail the conditions for the supply of gas and the method of calculating the damage caused by the unauthorised collection of gas, with the exception of Section 4 and Annex 1 to this Decree.
2. Decree No. 193 / 1995 Coll., laying down the method and amount of compensation for the limitation of property rights on forest land and forest land for outdoor electricity and gas pipelines.
3. Decree No. 318 / 1996 Coll., on the import of natural gas into the Czech Republic.
§ 11
Efficacy
This decree shall take effect on the day of its publication.
Minister:
Doc.

Příloha č. 1

Annex No 1 to Decree No 251 / 2001 Coll.
Principles for conversion of volume units into energy
1. The basis for charging the gas supply between the supplier and the customer is the supplied amount of energy. This amount of energy is the product of the average gross calorific value for the accounting period and the delivered gas volume, under the conditions set out in Section 1 (7).
2. Where, at a particular demand point in the transmission system or distribution system, there are time changes in the gross calorific value, the gross calorific value charged shall be determined as the weighted average of the gross calorific value supplied for the accounting period.
3. Where gas is supplied to customers from a single transfer point with a fluctuating energy value, the time averages of the gases by volume, the gas volumes supplied and the product of the volumes and the gases by volume (the amount of gas supplied) shall be determined. The weighted average of the gross calorific value for the entire accounting period is the sum of the amounts and gross calorific values of the gas delivered over the same period.
4. Where several sources of gas are supplied to the area which differ in volume by their gross calorific value, the weighted average of the gross calorific value of the gross calorific value for the accounting period shall be determined by the proportion of the sum of the energy delivered for the accounting period from each source and the sum of the total volumes of the gas delivered per year from those sources.
5. In exceptional cases where there are fluctuations in the gross calorific values (repairs, accidents, exceptional measures by technological operations of short-term nature, major random errors in the measuring equipment), for a limited period of up to 10 days within 12 months, these values of the gross calorific values shall not be taken into account in the calculation of the annual gross calorific values charged.
6. In the case of a volume-based gross calorific value in relation to the weighted monthly averages over the previous 12 months, not more than ± 4% shall be used to determine the average gross calorific value of the individual measuring points included in the separate supply system.
7. In the event that this derogation is greater than ± 4% for reasons other than those referred to in point 5, the operator concerned shall establish additional gas composition measuring points demonstrating compliance with the stable combustion heat in the tolerance referred to in point 6.
8. The detailed procedure for converting the volume units delivered and collected into energy is set out in the technical rules.

Příloha č. 2

Annex No 2 to Decree No 251 / 2001 Coll.
Method of determining the gas consumption for final customers, where it could not be detected either by subtracting the measuring equipment or by sending the completed data on a separate form of the operator of the relevant system
In order to determine the size of the gas collection for final customers, where it was not possible to detect it either by subtracting the measuring equipment or by sending the completed data on a special form of the operator of the relevant system or other in the gas supply contract in an agreed manner, the following percentage distribution of monthly withdrawals shall be used with the application of a proportion of less than a month.
(a) final customers with consumption above 720 m3 / year using gas for heating or heating in combination with hot water heating and stove
měsíc010203040506070809101112
%16,7214,2911,027,943,841,831,621,625,866,8310,5017,93
(b) final customers with a consumption not exceeding 720 m3 / year by evenly dividing the gas supply during the year;
(c) for the determination of non-measured gas sampling to end customers with a technological sampling, a uniform distribution of gas supply shall be used during the reading period.

Příloha č. 3

Annex No. 3 to Decree No 251 / 2001 Coll.
Time of use of appliances of the final customer
The number of hours of possible daily gas collection, taken as a basis for calculating the damage caused by unauthorised gas collection, is set to this extent
(a) for final customers with an annual collection not exceeding 6,000 m3
• for a gas cooker 2 hours a day,
• for a gas cooker 4 hours a day,
• for a gas refrigerator 24 hours a day,
• for a flow heater 3 hours a day,
• for gas heating except combined boilers May to September 4 hours a day, October to April 12 hours a day,
• for combined boilers May to September 7 hours a day, October to April 15 hours a day,
(b) for final customers with annual withdrawals over 6,000 m3
• for single-shift operations 8 hours a day,
• for two-shift operations 16 hours a day,
• 24 hours a day for continuous operation.
1) Act No. 505 / 1990 Coll., on Metrology, as amended.
2) Act No. 526 / 1990 Coll., on Prices, as amended.

Sign in for notes, favorites and notifications

Rating:

Comments 0

To write comments, please sign in.

Regulation Information

CitationDecree of the Ministry of Industry and Trade No. 251 / 2001 Coll., laying down the Rules for the operation of transmission and distribution systems in the gas industry
Regulation TypeOrder
Author-
CollectionCode of Laws
Date of Promulgation24.07.2001
Effective from24.07.2001
Effective until-
Status Valid
The regulation text is for informational purposes only.
Favorites
Browsing History